UK Scaffolding Inspection BS 5975 Compliance Checklist [FREE PDF]

Scaffolding inspections in the UK are governed by BS 5975:2019, the Work at Height Regulations 2005, and CDM Regulations 2015, requiring documented checks before first use, after adverse weather, and at least every 7 days. The duty holder must ensure all scaffolding is erected, altered, and dismantled by competent persons and that written inspection records are retained on site for three months. Failure to comply can result in HSE enforcement action, prohibition notices, and significant fines un

  • Industry: UK Construction
  • Frequency: Weekly
  • Estimated Time: 30-45 minutes
  • Role: Scaffolding Supervisor
  • Total Items: 34
  • Compliance: BS 5975:2019 Code of Practice for Temporary Works, Work at Height Regulations 2005 SI 2005/735, CDM Regulations 2015 SI 2015/51, HSE INDG411 - Working at Height, Health and Safety at Work Act 1974 s.2

Foundations and Base Plates

Verify that foundations are adequate to support the imposed loads and that base plates and sole boards are correctly installed.

  • Are all base plates correctly positioned and in full contact with sole boards?
  • Are sole boards of adequate size and in good condition without splits or damage?
  • Is the ground beneath the scaffold firm, level, and free from undermining or waterlogging?
  • Are standards vertical (plumb) within acceptable tolerances?
  • Are any foundation defects or concerns photographed and documented?

Tubes, Couplers, and Structural Integrity

Inspect all load-bearing tubes and couplers for condition, correct fitting, and structural adequacy.

  • Are all tubes free from significant corrosion, deformation, splits, or damage?
  • Are all couplers of the correct type (swivel, right-angle, putlog) for their load application?
  • Are all couplers tight, correctly seated on tubes, and showing no signs of slippage?
  • Are ledger and transom spacings within the design specification for the scaffold class?
  • Are any damaged or non-compliant tubes or couplers identified and removed from service?

Ties, Bracing, and Stability

Confirm that ties to the building structure and bracing arrangements comply with the scaffold design and relevant standards.

  • Are all ties present, correctly installed, and connected to sound anchorage points in the structure?
  • Is the tie pattern consistent with the design drawing or BS 5975 standard tie spacings?
  • Is diagonal bracing installed in accordance with the scaffold design in both plan and elevation?
  • Are rakers, buttresses, or other independent stability measures in good condition where ties cannot be provided?
  • Have any ties been removed or disturbed since the last inspection?

Working Platforms and Boards

Inspect all working platforms for full boarding, structural integrity, and freedom from trip hazards.

  • Are all working platforms fully boarded with no gaps exceeding 25mm between boards?
  • Are scaffold boards free from warping, splits, rot, or damage and correctly overlapping transoms?
  • Is the working platform width adequate for the work activity and passage of persons and materials?
  • Are platforms free from accumulation of debris, materials, or other obstructions?
  • Is a photograph taken of each working level platform condition?

Guard Rails, Toe Boards, and Edge Protection

Verify that all open edges and platforms are protected to prevent falls of persons and materials.

  • Are main guard rails installed at a height of 950-1150mm above the platform on all open edges?
  • Are intermediate guard rails or equivalent barrier installed so no gap exceeds 470mm?
  • Are toe boards of at least 150mm height in place at all working platform edges?
  • Are all guard rails secure and unable to be accidentally displaced or kicked out?
  • Is debris netting or brick guards fitted where required by the construction phase plan?

Access, Egress, and Ladders

Confirm that safe means of access to all working levels are provided and maintained in good condition.

  • Is a safe and suitable means of access provided to every working platform level?
  • Are staircase towers or internal ladders secured, in good condition, and at the correct angle?
  • Are all access hatches, trap doors, and landing boards correctly in place and not obstructed?
  • Is the scaffold clearly signed with load class, date of last inspection, and any restrictions?

Inspection Outcome and Record

Document the overall inspection outcome, defects identified, and actions required.

  • Has the scaffold passed this inspection and is it safe for use?
  • Have all defects observed been recorded with location and description?
  • Have any unsafe conditions resulted in the scaffold or sections being taken out of service?
  • Has the inspection report been passed to the duty holder or site manager within 24 hours?
  • Will a copy of this inspection record be retained on site for a minimum of 3 months?

Related Uk Construction Safety Checklists

Related Scaffolding Checklists

Why Use This UK Scaffolding Inspection BS 5975 Compliance Checklist [FREE PDF]?

This uk scaffolding inspection bs 5975 compliance checklist [free pdf] helps uk construction teams maintain compliance and operational excellence. Designed for scaffolding supervisor professionals, this checklist covers 34 critical inspection points across 7 sections. Recommended frequency: weekly.

Ensures compliance with BS 5975:2019 Code of Practice for Temporary Works, Work at Height Regulations 2005 SI 2005/735, CDM Regulations 2015 SI 2015/51, HSE INDG411 - Working at Height, Health and Safety at Work Act 1974 s.2. Regulatory-aligned for audit readiness and inspection documentation.

Frequently Asked Questions

What does the UK Scaffolding Inspection BS 5975 Compliance Checklist [FREE PDF] cover?

This checklist covers 34 inspection items across 7 sections: Foundations and Base Plates, Tubes, Couplers, and Structural Integrity, Ties, Bracing, and Stability, Working Platforms and Boards, Guard Rails, Toe Boards, and Edge Protection, Access, Egress, and Ladders, Inspection Outcome and Record. It is designed for uk construction operations and compliance.

How often should this checklist be completed?

This checklist should be completed weekly. Each completion takes approximately 30-45 minutes.

Who should use this UK Scaffolding Inspection BS 5975 Compliance Checklist [FREE PDF]?

This checklist is designed for Scaffolding Supervisor professionals in the uk construction industry. It can be used for self-assessments, team audits, and regulatory compliance documentation.

Can I download this checklist as a PDF?

Yes, this checklist is available as a free PDF download. You can also use it digitally in the POPProbe mobile app for real-time data capture, photo documentation, and automatic reporting.

Browse More Checklists