Solar PV System Commissioning Checklist
This solar PV system commissioning checklist ensures compliance with IEC 62446-1 (PV System Commissioning), NEC Article 690 (Solar PV Systems), IEEE 1547 (Interconnection Standards), and NFPA 70E electrical safety requirements. Designed for solar project managers, EPC contractors, and electrical engineers to verify that a newly installed PV system meets design specifications, safety codes, and utility interconnection requirements before energization.
- Industry: Renewable Energy
- Frequency: Per Event
- Estimated Time: 3-6 hours
- Role: Solar Project Manager / EPC Electrical Engineer
- Total Items: 30
- Compliance: IEC 62446-1 PV System Commissioning Documentation, NEC Article 690 Solar Photovoltaic Systems, IEEE 1547 Interconnection and Interoperability, NFPA 70E Electrical Safety in the Workplace, UL 1741 Inverter Standard
Pre-Energization Checks
Verification before system is energized.
- Building/electrical permit signed off by AHJ?
- As-built configuration matches approved design drawings?
- All required NEC 690 labels installed?
- System grounding and bonding per NEC 690.47 complete?
- Rapid shutdown system installed per NEC 690.12?
String and Module Testing
DC circuit testing per IEC 62446.
- Open circuit voltage (Voc) measured and within tolerance?
- Short circuit current (Isc) tested per string?
- Insulation resistance tested (>1 MOhm per IEC 62446)?
- String polarity verified before connecting to inverter?
- Irradiance level recorded during testing (W/m²)
Inverter Commissioning
Inverter programming and grid connection verification.
- Inverter settings configured per utility interconnection agreement?
- Grid voltage and frequency within acceptable range?
- Anti-islanding protection tested and confirmed?
- Export limit programmed if required by utility?
- Inverter communication (Modbus, SunSpec) configured?
AC-Side Electrical Verification
AC wiring, overcurrent protection, and metering.
- AC disconnect installed and labeled per NEC 690?
- Overcurrent protection devices correctly rated?
- Production meter installed and programmed?
- Net/bidirectional meter installed by utility?
- Backfeed protection for utility confirmed?
Monitoring and Data Collection
System monitoring platform commissioning.
- Monitoring platform online and receiving data?
- Baseline production target entered in monitoring system?
- Performance alerts configured?
- Owner/operator access to monitoring portal confirmed?
- On-site weather station or irradiance sensor calibrated?
Documentation and Handover
Commissioning report and owner documentation.
- As-built drawings provided to owner?
- Equipment warranties registered and provided?
- O&M manual provided to owner/operator?
- IEC 62446 commissioning report completed?
- Owner/operator training completed?
Related Renewable Energy Checklists
- Solar Rooftop Work Safety Checklist
- Solar String Inverter Preventive Maintenance Checklist
- Utility-Scale Solar Farm O&M Inspection Checklist
- Solar + Battery Energy Storage System (BESS) Checklist
- Agrivoltaic / Dual-Use Solar Site Inspection Checklist
- Solar Carport/Canopy Inspection Checklist
- Solar Panel Cleaning and Soiling Management Checklist
- Floating Solar (Floatovoltaic) System Inspection Checklist
Related Solar Checklists
- Solar PV System Daily Inspection Checklist - FREE Download
- Solar Thermal System Inspection Checklist - FREE Download
- Solar Rooftop Work Safety Checklist - FREE Download
- Solar String Inverter Preventive Maintenance Checklist - FREE Download
- Utility-Scale Solar Farm O&M Inspection Checklist - FREE Download
- Solar + Battery Energy Storage System (BESS) Checklist - FREE Download
- Agrivoltaic / Dual-Use Solar Site Inspection Checklist - FREE Download
- Solar Carport/Canopy Inspection Checklist - FREE Download
- Solar Panel Cleaning and Soiling Management Checklist - FREE Download
- Floating Solar (Floatovoltaic) System Inspection Checklist - FREE Download
Why Use This Solar PV System Commissioning Checklist?
This solar pv system commissioning checklist helps renewable energy teams maintain compliance and operational excellence. Designed for solar project manager / epc electrical engineer professionals, this checklist covers 30 critical inspection points across 6 sections. Recommended frequency: per event.
Ensures compliance with IEC 62446-1 PV System Commissioning Documentation, NEC Article 690 Solar Photovoltaic Systems, IEEE 1547 Interconnection and Interoperability, NFPA 70E Electrical Safety in the Workplace, UL 1741 Inverter Standard. Regulatory-aligned for audit readiness and inspection documentation.
Frequently Asked Questions
What does the Solar PV System Commissioning Checklist cover?
This checklist covers 30 inspection items across 6 sections: Pre-Energization Checks, String and Module Testing, Inverter Commissioning, AC-Side Electrical Verification, Monitoring and Data Collection, Documentation and Handover. It is designed for renewable energy operations and compliance.
How often should this checklist be completed?
This checklist should be completed per event. Each completion takes approximately 3-6 hours.
Who should use this Solar PV System Commissioning Checklist?
This checklist is designed for Solar Project Manager / EPC Electrical Engineer professionals in the renewable energy industry. It can be used for self-assessments, team audits, and regulatory compliance documentation.
Can I download this checklist as a PDF?
Yes, this checklist is available as a free PDF download. You can also use it digitally in the POPProbe mobile app for real-time data capture, photo documentation, and automatic reporting.