Solar PV System Commissioning Checklist

This solar PV system commissioning checklist ensures compliance with IEC 62446-1 (PV System Commissioning), NEC Article 690 (Solar PV Systems), IEEE 1547 (Interconnection Standards), and NFPA 70E electrical safety requirements. Designed for solar project managers, EPC contractors, and electrical engineers to verify that a newly installed PV system meets design specifications, safety codes, and utility interconnection requirements before energization.

  • Industry: Renewable Energy
  • Frequency: Per Event
  • Estimated Time: 3-6 hours
  • Role: Solar Project Manager / EPC Electrical Engineer
  • Total Items: 30
  • Compliance: IEC 62446-1 PV System Commissioning Documentation, NEC Article 690 Solar Photovoltaic Systems, IEEE 1547 Interconnection and Interoperability, NFPA 70E Electrical Safety in the Workplace, UL 1741 Inverter Standard

Pre-Energization Checks

Verification before system is energized.

  • Building/electrical permit signed off by AHJ?
  • As-built configuration matches approved design drawings?
  • All required NEC 690 labels installed?
  • System grounding and bonding per NEC 690.47 complete?
  • Rapid shutdown system installed per NEC 690.12?

String and Module Testing

DC circuit testing per IEC 62446.

  • Open circuit voltage (Voc) measured and within tolerance?
  • Short circuit current (Isc) tested per string?
  • Insulation resistance tested (>1 MOhm per IEC 62446)?
  • String polarity verified before connecting to inverter?
  • Irradiance level recorded during testing (W/m²)

Inverter Commissioning

Inverter programming and grid connection verification.

  • Inverter settings configured per utility interconnection agreement?
  • Grid voltage and frequency within acceptable range?
  • Anti-islanding protection tested and confirmed?
  • Export limit programmed if required by utility?
  • Inverter communication (Modbus, SunSpec) configured?

AC-Side Electrical Verification

AC wiring, overcurrent protection, and metering.

  • AC disconnect installed and labeled per NEC 690?
  • Overcurrent protection devices correctly rated?
  • Production meter installed and programmed?
  • Net/bidirectional meter installed by utility?
  • Backfeed protection for utility confirmed?

Monitoring and Data Collection

System monitoring platform commissioning.

  • Monitoring platform online and receiving data?
  • Baseline production target entered in monitoring system?
  • Performance alerts configured?
  • Owner/operator access to monitoring portal confirmed?
  • On-site weather station or irradiance sensor calibrated?

Documentation and Handover

Commissioning report and owner documentation.

  • As-built drawings provided to owner?
  • Equipment warranties registered and provided?
  • O&M manual provided to owner/operator?
  • IEC 62446 commissioning report completed?
  • Owner/operator training completed?

Related Renewable Energy Checklists

Related Solar Checklists

Why Use This Solar PV System Commissioning Checklist?

This solar pv system commissioning checklist helps renewable energy teams maintain compliance and operational excellence. Designed for solar project manager / epc electrical engineer professionals, this checklist covers 30 critical inspection points across 6 sections. Recommended frequency: per event.

Ensures compliance with IEC 62446-1 PV System Commissioning Documentation, NEC Article 690 Solar Photovoltaic Systems, IEEE 1547 Interconnection and Interoperability, NFPA 70E Electrical Safety in the Workplace, UL 1741 Inverter Standard. Regulatory-aligned for audit readiness and inspection documentation.

Frequently Asked Questions

What does the Solar PV System Commissioning Checklist cover?

This checklist covers 30 inspection items across 6 sections: Pre-Energization Checks, String and Module Testing, Inverter Commissioning, AC-Side Electrical Verification, Monitoring and Data Collection, Documentation and Handover. It is designed for renewable energy operations and compliance.

How often should this checklist be completed?

This checklist should be completed per event. Each completion takes approximately 3-6 hours.

Who should use this Solar PV System Commissioning Checklist?

This checklist is designed for Solar Project Manager / EPC Electrical Engineer professionals in the renewable energy industry. It can be used for self-assessments, team audits, and regulatory compliance documentation.